City HallTuesday, November 24
State regulators heard from residents on the Project Atlas data center Monday night
The Daily Allentown team
If you missed it, state regulators held a public meeting and hearing Monday night at Cedar Crest College on Project Atlas, the proposed hyperscale data center in South Whitehall Township. Dozens turned out. The site sits across from Parkland High School.
Project Atlas would cover roughly 410 acres
Area of Project Atlas, beside places you know
310 football fields would fit inside Project Atlas
Source: Lehigh Daily
View as table
| Area | |
|---|---|
| Project Atlas | 410 acres (proposed campus site) |
| A football field | 1.3 acres (end zones included) |
The Pennsylvania Department of Environmental Protection is reviewing two permits, one for construction stormwater runoff and one for work near wetlands and local waterways, Lehigh Daily reports. The South Whitehall Civic Alliance said before the hearing its worries include wetlands on the site and stormwater planning during construction.
- Developer: CDE Acquisitions LLC, an affiliate of Edged
- Size: 1.5 million square feet on roughly 410 acres
- Plan: three data center buildings, an administration building, a warehouse
DEP is now weighing the comments as it decides whether to issue permits. The project also needs a green light from South Whitehall Township, which has until Feb. 28 to act. The plans go back to the township's planning commission Jan. 13.
Project Atlas has two more local dates ahead
- Nov. 23DEP held a public meeting and hearing at Cedar Crest College
- Jan. 13Plans are scheduled back before the township planning commission
- Feb. 28Deadline for South Whitehall Township to act on the plan
Source: WFMZ
Sources: Lehigh Daily, WFMZ